b) 23-0025 CONFERENCE WITH LEGAL COUNSEL:
Anticipated Litigation - Government Code Section 54956.9(d)(2)&(3)
The City finds, based on advice from legal counsel, that discussion in open session will prejudice the City in the litigation.
Significant exposure to civil litigation* - Two Matters:
1) Delay Claim by EBS General Engineering, Inc. ("EBS"): Pacific Coast Highway Improvements at Aviation Blvd & Pier Ave Project.
2) Additional Compensation Claim by Aid Builders Inc. ("Aid"): Public Park Restroom Project.
*Significant exposure to civil litigation means that there exists facts and circumstances where the City may face a lawsuit. This does not mean that any potential lawsuit is meritorious or that there is a significant risk that the City will not prevail in any possible lawsuit.